ru / en

Process units presentation by "Peton" for Amur GPP

2014-09-06

Presentation of process units for Amur GPP and helium plant was held in the head office of NIPI NG “Peton” on the 4th and the 5th of September 2014.

Participants of presentation:

  • “Gazprom pererabotka” (Surgut city),
  • “VNIPIgazdobycha” (Saratov city),
  • “Gazprom VNIIGAZ” (Moscow city) 
  • “Gazprom” (via conference) – department of marketing, gas and liquid hydrocarbons processing.

Presentation consisted of:

  • Plant construction concept, product treatment units layout and dimensions were reviewed and approved;  
  • Engineering solutions on gas treatment facilities were considered and approved (separation unit, treatment unit, dehydration unit);
  • Technical regulations of the plant were considered and approved;
  • Deadlines for project documentation submission were determined.